← International portfolio

Turkmenistan / Strategic capital · phased delivery

31.25 MW liquid-cooled data center.

Project profit participation / 84-month model

A three-stage industrial facility in the Balkan Region, combining low modeled power cost, liquid-cooled infrastructure and an investor-first profit waterfall.

Project CAPEX$24.68M
Participation$5M–$24.68M
Pre-payback share70% to investor
Modeled payback~47 months
01

Investment case

Operating logic before financial optics.

The underwriting case is built around power cost, deployment milestones, control of the equipment and measurable operating performance. Headline economics remain modeled and indicative.

01 / POWER

Low modeled energy cost

The base case uses approximately $0.023/kWh, 95% uptime and 1.15 PUE. Final tariff and supply terms remain subject to diligence.

02 / PHASING

6.25 to 31.25 MW

Capacity is commissioned in three stages: 6.25 MW, 12.5 MW and 31.25 MW, aligning capital deployment with operating milestones.

03 / ENGINEERING

Liquid-cooled infrastructure

The design uses a centralized two-loop liquid-cooling system within a purpose-built industrial facility.

04 / ALIGNMENT

Investor-first waterfall

The modeled investor share is 70% before capital repayment and 30% after repayment, subject to definitive documentation.

02

Transaction structure

Capital aligned with identifiable assets.

Final economics, security, governance, eligibility and closing conditions are established only in definitive transaction documents.

Structuring entity
WAYMORR INC., Delaware C-Corporation
Local execution
Local project operator responsible for construction, permits and operations
Instrument
Project profit participation, subject to definitive documentation
Target participation
$5M–$24.68M, subject to structuring
Profit waterfall
70% to investor pre-repayment; 30% post-repayment
Asset alignment
Equipment under an investor-aligned lease until capital repayment
03

Modeled economics

Numbers with their assumptions attached.

These figures are planning outputs, not forecasts or guarantees. Results can vary materially with digital-asset price, network difficulty, power, uptime and commissioning.

Project CAPEX$24.68M

Modeled equipment and construction requirement at full scope.

Modeled power$0.023/kWh

Planning assumption requiring confirmation in project agreements.

Investor payback~47 mo.

Modeled repayment of invested capital under the 70% pre-payback share.

Project payback~33 mo.

Modeled project-level accumulated profit reaching CAPEX.

Full capacity31.25 MW

Three-stage build-out from 6.25 MW to 12.5 MW to 31.25 MW.

EquipmentUp to 5,550

Liquid-cooled ASIC units at the full planned deployment.

04

Preliminary delivery roadmap

Capital follows commissioning milestones.

Timing is preliminary and shifts with financing, power agreements, procurement, permitting and site readiness.

01

Close capital & finalize project package

Complete financing, diligence, definitive documents and execution prerequisites.

02

Build phase one

Begin construction and procurement for the first 6.25 MW deployment.

03

Commission 6.25 MW

Launch the initial operating stage with approximately 1,110 units.

04

Expand to 12.5 MW

Commission the second stage after phase-one operating validation.

05

Reach 31.25 MW

Complete the third stage with up to approximately 5,550 units at full scope.

05

Risk factors & controls

Downside is part of the mandate.

Digital infrastructure and digital-asset-related projects involve substantial risk, including possible loss of capital.

Country & regulatory

Permitting, local regulation, currency, enforcement and policy changes may affect delivery and economics.

Power & interconnection

The tariff, available capacity and grid conditions require contractual and technical confirmation.

Construction

A multi-stage industrial build is exposed to schedule, contractor, logistics and cost-overrun risk.

Digital-asset market

BTC price, network difficulty and halving effects can materially change revenue.

Counterparty & governance

Control, reporting, lease rights and distributions depend on enforceable definitive agreements.

Loss of capital

Modeled returns and repayment are not guaranteed; investment capital is at risk.

QUALIFIED COUNTERPARTIES

Review the full project file.

This project profile is for informational purposes only and is intended for qualified counterparties. It does not constitute an offer to sell, or a solicitation of an offer to buy, any security or financial instrument. All financial figures are modeled and indicative, subject to due diligence and definitive documentation, and are not guarantees of future performance. Investment involves substantial risk, including possible loss of capital.